Project summary

Client name: Ausenco Downer Joint Venture
Project name: Carrapateena
Location: South Australia
Commenced: March 2019

Project requirements

TIAM was engaged by Ausenco Downer Joint Venture (ADJV) to assist in the installation of a SAG and Ball Mill at Carrapateena Mine Site located in South Australia.

TIAM Solutions was awarded a service agreement for the provision of technical support in relation to the SAG and Ball Mill Installation at the Carrapateena Project. TIAM commenced work on the Carrapateena project in March 2019 and completed this project in December 2019. The project ran for a 10-month period.

Key deliverables

To assist in the successful installation of a SAG Mill and Ball Mill for the client within the request timeframe.

Project outcomes

To assist in the successful installation of a SAG Mill and Ball Mill for the client within the request timeframe.

Outotec Ball Mill
9500kW 6.7x 10.97m Egl

Outotec SAG Mill
7000kW 8.5 x 4.57m Egl